The work of the "pool maintenance" is changing rapidly. These days, it takes more than a bucket of chlorine and a scrubbing brush to maintain a pool of multiple standards customers expect.
The endless pool (Infinity Pools) separate location very suitable for underwater fun. These are man-made ​​pool for entertainment purposes, but there are some very special.
Swimming pool and the water is often absorbed places because direct contact with water and the solution. Therefore, waterproofing and swimming pool water is inevitable. Waterproof to water leakage to the outside, resistant to water and dirt.

Process Waterproofing Pool, Pools


Waterproofing solution for this type of work proposed as follows:

A. Use product Norlic-02:

Norlic-02 is a combination of inorganic compounds water-based liquid milk white. Norlic-02 when combined with cement to the surface scan, Sealing the pores (capillaries) in the concrete and other surfaces for surface becomes solid, able to stretch marks tingle small waterproof increase.

Product Norlic - 02 has a very high elasticity and good heat resistance.

B. Methods of construction:

Waterproofing Co., Ltd Truong Thinh send you waterproof construction process underground works as follows:

ITEMS: WATERPROOF FLOOR bottom of the pool, the pool

I. WORK SURFACE PREPARATION:

- Filling of defects on the surface of the plaster concrete, Basketball, cracks, ...

- Coating trim excess concrete, convex, ...

- Clean the dirt and grease on the surface.

- Water spray, moisture on the surface of the floor and walls.

II. WATERPROOFING CONSTRUCTION STEPS.

    Materials used:

- Waterproofing Products dedicated Norlic - 02.

- Waterproof cement.

    Methods of construction:

- Scan class Norlic - 02 pure on the surface.

- When class Norlic - 02 surface dry (about 30 minutes), scan a class Norlic - 02 waterproof cement mix (1:3 ratio).

- When class Norlic - 02 mixed with dry cement surface (about 3 hours), scan a class Norlic - 02 mixed with waterproof cement (1:3 ratio).

- Fill the mortar waterproof protection after completion.

III. WATERPROOFING DETAILS THE LOCATION AS FOLLOWS:

A.> NAIL

The preparation:

- Poured concrete pit wall (built of bricks) and plastered flat bowl.

- Water treatment coral cover 1 layer of concrete lining at least 5 cm thick and is made flat.

- In the middle of the floor and the walls of the pool processors need to create shoulder instead of right angles.

- The waterproof layer to scroll down the entire wall of the pit and covered the floor of the bottom of the foundation a minimum of 15-20cm

- After finishing waterproofing need plastering plastering, plaster protection at least 3cm thick to protect absolute not to be punctured membrane in steel construction time.

B.> BEAMS

The preparation:

- Beam wall was built of bricks and plastered flat bowl.

- Floor basement floor on the surface of cells to undergo one concrete lining at least 5 cm thick and is made flat.

- In the middle of the floor and walls of the beams need to create shoulder instead of right angles.

- Waterproofing layer must scroll down the entire floor and wall beams (membrane coated beams).

- After finishing waterproofing need plastering plastering, plaster protection at least 30mm thick to protect absolute not to be punctured membrane in steel construction time.

C.> adjoining BEAMS AND borrowers

The preparation:

- Wall beam built of bricks and plastered flat bowl.

- In the middle of the floor and wall beams need to create the shoulder instead of right angles.

- The waterproof layer to wrap the whole beam from the wall through the book associated with waterproofing floor

- After finishing waterproofing need plastering plastering, plaster protection at least 30mm thick to protect absolute not to be punctured membrane in steel construction time.

- The end of the membrane (the intersection of the floor and walls (all around the wall) must be ice water resistance (bentonite / rubber expansion before concreting six hours)

NOTE:

- At the location of the wastewater treatment tank floor, waterproof membrane must be sealed form the first fully sealed bags for water treatment tank bottom floor.

ITEMS: WATERPROOF WALL pool, WATER

I.> SURFACE PREPARATION WORK.

- Filling of defects on the surface of the plaster concrete, Basketball, ...

- Coating trim excess concrete, convex, ...

- Iron Removal television, iron mirrors, ...

- Clean the dirt and grease on the surface.

II.> WATERPROOFING CONSTRUCTION STEPS.

1.> Materials used:

- Waterproofing Products dedicated Norlic - 02.

- Waterproofing admixture.

- Cement.

2. > Method of application: wall surface 3 layers covered with brush (or roller).

Soaked wet surface prior to construction.

- Scan class Norlic - 02 pure on the surface.

- When class Norlic - 02 surface dry (about 30 minutes), scan a class Norlic - 02 waterproof cement mix (1:3 ratio).

- When class Norlic - 02 mixed with dry cement surface (about 3 hours), scan a class Norlic - 02 waterproof cement mix (1:3 ratio).

- Fill the mortar waterproof protection after completion.

- After finishing the delivery unit to paint plaster mastic and paint finish.

* Note:

    Areas require the entire floor waterproofing tanks, wall to scan government is higher than the ground outside at least 30 cm.
    Need rigorous mixing ratio and the level of material / waterproof area.
    Must satisfy requirements on hygiene grounds.


Other news

KI TI CONSTRUCTION & TRADING CO., LTD
Head office : 85/27 Nguyen The Truyen Street , Tan Son Nhi Ward ,Tan Phu District, HCMC
Hotline         : 0919 558 689 
Tel                : (84.28) 3812.0738 - Fax: (84.28) 3812.0739 
Website       : www.kitipool.com , www.kitipool.vn    

Email          : kitipools@gmail.com 

Design by: Tri Viet